Straight from the horse’s mouth, here is the final schedule of SM Supermalls’ projects in Mindanao:
May 2010 – Start of construction of SM City Lanang in Davao City. Final design has just been approved.
June 2010 - Start of construction of SM City General Santos. Final design has just been approved.
SM City Lanang and SM City General Santos will be finished in 10 months and will open in the 11th month.
June 2010 – Renovation of SM City Cagayan de Oro will start.
Theme: Earth Colors
Time Frame: 1.5 years
June 2010 – Start of Renovation (Existing Mall) and Expansion (Whole of Parking D – 4 level expansion building; covered carpark building will be a different project)
Theme: Black and White
Time Frame: 1.5 years
repost from: xzibit31 of SkyscraperCity

Wow! Is this for real? hehe, joke lang. Can you post the design of SM GenSan & SM Lanang? I know a lot of Generals & Davaoenos are already excited of this news. Thanks
not knew inDavao city, coz its a 2nd sm mall
It is already confirmed… Pile Driving is already started last November, Construction will start this January 2011, Target Opening Date will be March 2012… Same target opening of (Ayala Center Davao) Phase 2…. Meanwhile lets focus in (Ayala Center Davao) Phase 1 – Abreeza Mall, it will be the biggest mall when it opens this May 2011… But SM Lanang Davao will be bigger (twice bigger than SM Ecoland Davao) kac may IMAX… Kudos to davao….
its supermall, one of the biggest mall in mindanao…..